Skip to content

Better Infrastructure

Apex Road Reservoir

Construction of a four megalitre reservoir to be built off Apex Road adjacent to the existing reservoir in Bottlebrush Park is set to begin, with the contractor, Hornicks Constructions, securing the site from January 29. The new reservoir is required to address water security and to cater for the predicted population growth within the town of Gunnedah. The project cost is $2.5 million and will be fully-funded by Council. The project involves the construction of a concrete reservoir, which will be approximately 27.5 metres in diameter and approximately eight metres high. The reservoir has been designed to have the same roof level as the existing reservoir and will incorporate aesthetic improvements, including white roof sheeting to reduce glare to surrounding residences. The project is expected to take 36 weeks. Working hours will be undertaken between 7:00am and 6:00pm, Monday to Friday and between 8:00am and 1:00pm on Saturdays.

10/07/2018 - The base slab for the 4ML Apex Road Reservoir was poured on Thursday, 14 June – comprising of 95m3 of concrete and approximately nine tonnes of reinforcing steel. Due to the cold weather a variety of measures have been put in place to allow the concrete to cure and to prevent it from shrinking, or cracks forming on the surface. The first concrete wall pour is scheduled for Monday, 16 July – approximately 70m3 of concrete. The aluminium roof framing and sheeting is scheduled for late August 2018, with the project on schedule to be completed by November 2018.

 

Curlewis Pipeline Project

The $5.9 million Curlewis Pipeline Project will improve water quality, storage capacity and water security for the village. The Curlewis Pipeline Project involves the ins...

Apex Road Reservoir

Construction of a four megalitre reservoir to be built off Apex Road adjacent to the existing reservoir in Bottlebrush Park is set to begin, with the contractor, Hornicks Cons...

Donnelly Sports Field Lighting Upgrade

Donnelly Fields will soon be under lights after Gunnedah Shire Council awarded the contract for the supply and installation of lighting to REES Electrical Pty Ltd in December....

Blackjack Creek Flood Mitigation Project

Works to protect the Wandobah Road area from future flood events has commenced. Gunnedah Shire Council resolved to accept a tender from Daracon Group Gunnedah to und...

Gunnedah Memorial Pool Complex Upgrade

Gunnedah Shire Council accepted a tender of $11.4 million from Hines Constructions of Bathurst to complete Stage 1a of the Master Plan at the Council Ordinary Meeting on 16 Au...

Urban Roads

Bloomfield StreetPreparing the heavy vehicle alternate route for a sustainable future, by enhancing the road pavement, and wearing surface to discard water whilst providing a...

Better Infrastructure

Apex Road Reservoir

Construction of a four megalitre reservoir to be built off Apex Road adjacent to the existing reservoir in Bottlebrush Park is set to begin, with the contractor, Hornicks Constructions, securing the site from January 29. The new reservoir is required to address water security and to cater for the predicted population growth within the town of Gunnedah. The project cost is $2.5 million and will be fully-funded by Council. The project involves the construction of a concrete reservoir, which will be approximately 27.5 metres in diameter and approximately eight metres high. The reservoir has been designed to have the same roof level as the existing reservoir and will incorporate aesthetic improvements, including white roof sheeting to reduce glare to surrounding residences. The project is expected to take 36 weeks. Working hours will be undertaken between 7:00am and 6:00pm, Monday to Friday and between 8:00am and 1:00pm on Saturdays.

10/07/2018 - The base slab for the 4ML Apex Road Reservoir was poured on Thursday, 14 June – comprising of 95m3 of concrete and approximately nine tonnes of reinforcing steel. Due to the cold weather a variety of measures have been put in place to allow the concrete to cure and to prevent it from shrinking, or cracks forming on the surface. The first concrete wall pour is scheduled for Monday, 16 July – approximately 70m3 of concrete. The aluminium roof framing and sheeting is scheduled for late August 2018, with the project on schedule to be completed by November 2018.

 

Curlewis Pipeline Project

The $5.9 million Curlewis Pipeline Project will improve water quality, storage capacity and water security for the village. The Curlewis Pipeline Project involves the ins...

Apex Road Reservoir

Construction of a four megalitre reservoir to be built off Apex Road adjacent to the existing reservoir in Bottlebrush Park is set to begin, with the contractor, Hornicks Cons...

Donnelly Sports Field Lighting Upgrade

Donnelly Fields will soon be under lights after Gunnedah Shire Council awarded the contract for the supply and installation of lighting to REES Electrical Pty Ltd in December....

Blackjack Creek Flood Mitigation Project

Works to protect the Wandobah Road area from future flood events has commenced. Gunnedah Shire Council resolved to accept a tender from Daracon Group Gunnedah to und...

Gunnedah Memorial Pool Complex Upgrade

Gunnedah Shire Council accepted a tender of $11.4 million from Hines Constructions of Bathurst to complete Stage 1a of the Master Plan at the Council Ordinary Meeting on 16 Au...

Urban Roads

Bloomfield StreetPreparing the heavy vehicle alternate route for a sustainable future, by enhancing the road pavement, and wearing surface to discard water whilst providing a...